Excavation for the footings and foundation walls began only to find shallow ledge rock, requiring the foundation to be moved about 8 ' to the northeast. Below the main floor, a 2 ' 6" crawl space will be used to provide space for a 40 gallon electric hot water heater and a pressure tank for the water supply system. Most of the electrical service will be supplied from the crawl space.
![](http://photos1.blogger.com/blogger/6461/1373/320/Footings.jpg)
The foundation walls are 8" thick poured concrete with insulation board forms. The forms were tied together with a plastic tie system which held the forms in place while the wet concrete was still fluid. The top of the 8" concrete wall was reinforced with two #4 bars to minimize any vertical wall cracking.
After the foundation wall was poured, 1/2" anchor bolts were placed in the top of the poured concrete wall to anchor a treated wood sill plate for the wood floor system which will be contructed next.
![](http://photos1.blogger.com/blogger/6461/1373/320/Concrete%20Poured.jpg)
The insulation board forms were left in place to provide insulation for the crawl space. The outside face of the insulation board will be coated with a heavy textured coating which will protect the insulation board from weathering and UV rays of the sun.